1.Standard Installation Duration

The SkyTherm® Roof System is advertised with a standard installation timeframe of 2 to 3 working days. This timeframe is based on a typical conservatory size of approximately 12 square metres (12m²) and under ideal installation conditions.

2.Scope and Assumptions

This estimated installation duration assumes the following:

2.1 Property Size & Structure
The timings stated are based on a 12m² and features a standard roof structure requiring no structural modifications or reinforcements.

2.2 Site Readiness
The customer must ensure that the conservatory interior is cleared of furniture and other obstructions on the exterior of the conservatory before the start of the installation. Delays in preparing the site may impact the timeframe.

2.3 Absence of Unforeseen Issues
No structural damage, deterioration, or issues are discovered upon removal of the existing roof. If unforeseen complications arise, the timeframe may be extended to accommodate remedial work.

2.4 Weather Dependency
Aspects of the SkyTherm® installation process (such as the application of the EPDM roof membrane) require dry weather conditions. Installations may be rescheduled due to poor weather, and CI Group cannot be held responsible for delays caused by adverse weather conditions.

2.5 Property Access
Adequate and safe access to the installation site must be available. Limited or obstructed access may cause delays to the delivery of materials or execution of works.

3.Non-Standard Installations

Larger conservatories, bespoke roof specifications, multiple lanterns, or unique design considerations may require a longer installation period. Your CI Group representative will advise on expected timeframes based on your individual project requirements.

4.Customer-Induced Delays

CI Group reserves the right to revise the installation schedule if delays are caused by:

  • Changes to the agreed specifications
  • Incomplete site readiness
  • Lack of access to the property during working hours

5.General Conditions

The 2–3 day timeframe is provided as a guideline and not as a guaranteed duration. It is offered in good faith based on previous standard installations and is subject to change depending on the variables outlined above.